Project Details
Client: Confidential
Location: Paris, France
Solution provided:
Project type: Load Bank Commissioning
Paris Data Centre Phase 2
Overview
As part of a critical commissioning phase for a new data centre facility in Paris, PowerLoad successfully deployed a 500kW Load Bank Unit in conjunction with our 10-Spigot Manifold System.
This deployment was conducted over a 3-week period, simulating the thermal and electrical load of 10 fully populated server racks to validate the infrastructure’s capacity and cooling performance under realistic operating conditions.
The system was engineered for precision and efficiency, enabling seamless integration with the facility’s cooling network and delivering reliable, controlled test results. As a result, the client can now proceed with confidence, knowing that their cooling systems have been rigorously tested to meet design intent, ensuring robust performance under operational loads.