Base build

Base build testingLB500LB600LB700ACLB 200Standard or solid-state switching

End-of-line

End-of-line testingLCLB 160LCLB 240ACLB 60

Applications

Cooling

Chillers and cooling plantStatic and dynamic load testing

Power

UPS systemsGeneratorsSwitchgear and power qualityProtection settings

Explained

Liquid coolingGPU load testingWater qualityLoop monitoringCommissioning

Equipment

Commissioning equipment

Manifold trolleyFlushing & refill cart

Tools

The full rangeSizing calculatorDatasheets

Services

Commissioning supportLoad bank hireHigh load simulationBespoke load banksSupply and installationMaintenance and repairDeployment and managementBuy or hireProjects

Company

AboutPartnersProjectsAcademyNewsEventsFAQ Speak to the team
Chillers and cooling plant

Chillers and cooling plant

A chiller that handles its rated heat has proven capacity. The load now changes quickly, so the whole cooling system has to be shown responding, as the heat rises and as it falls.

PowerLoad manifold rig connected into the coolant loop in a data hall
ChillersCDU and risers proven
BothDirections tested
2Ranges used
RackPosition tested

Testing chillers and cooling plant means putting a controllable heat load into the system and watching how the whole chain responds: chillers, CDU, pumps, control valves, sensors and controllers. Base build testing proves the plant has the capacity while the hall is built. End-of-line testing replicates the heat at each rack position, so the response to a change is proven in both directions before the GPUs are installed.

What it shows

What the test shows

Capacity is one result. The rest is how the system behaves when the load moves.

Capacity

The chillers, CDU and risers carry the full IT heat load at the design condition.

Response

How the plant follows the heat as it rises, and as it suddenly reduces.

Control

Pumps, control valves, sensors, controllers and communications working together.

Position

Flow, pressure and temperature at each rack, not a hall average.

Which range

Base build first, end-of-line second

The two ranges answer different questions, and a hall usually needs both.

Equipment

What is used

Heat is rejected into the coolant loop, so the plant is tested exactly as the racks will load it.

  • LB500, LB600 or LB700 for base build heat load
  • LCLB 160 or LCLB 240 at rack level
  • ACLB 60 for rack-format air heat
  • Manifold trolley to distribute coolant to the load banks
  • Flushing and refill cart to clean the loop and prove it clean first
  • Live flow, temperature and pressure logged from one controller
Coolant valves and instrumentation during a liquid cooling test
FAQ

Chillers and cooling plant, answered

Yes. The liquid-cooled load banks reject heat into the coolant loop. The 700kW LB700 suits chiller and larger cooling plant testing where a heavier heat load is needed.
A liquid-cooled load bank rejects its heat into the loop as the racks will, so the CDU, manifold and risers are exercised under real heat months before any accelerator arrives.
Because flow and temperature are not uniform across a hall. A hall average can pass while one rack runs outside its limits.
Usually. Not every component in a server is liquid cooled, and some of the heat still needs air cooling. The ACLB 60 replicates that heat at the rack.
Related

Related applications

Test the cooling plant against a realistic heat profile

Tell us the cooling design and the IT load. We will advise on the heat load for the plant.