Two load banks, one manifold
The animation shows two 500kW load banks, a 1MW kit, connected into a manifold trolley that distributes coolant to its outlets.
Each outlet stands for a provisioned server rack in the hall, so you test the arrangement the building will actually run, not an equivalent load somewhere convenient.
Independent control at every outlet
An isolation valve at every outlet lets each rack be controlled on its own.
One can be isolated, adjusted or dropped from the test without disturbing the rest, so a fault can be investigated while the run continues.
The return path through the CDU
Flow from each outlet returns through the CDU, closing the loop through the same equipment that serves the racks in production.
Testing the return matters as much as the supply. A set-up that proves delivery to the rack but not the return has tested half the circuit.
Testing multiple racks simultaneously
Several racks can be tested together while flow and return stay under full control.
Testing together shows how outlets interact. Circuits that perform alone can still starve one another when they all draw at once.