Base build

Base build testingLB500LB600LB700ACLB 200Standard or solid-state switching

End-of-line

End-of-line testingLCLB 160LCLB 240ACLB 60

Applications

Cooling

Chillers and cooling plantStatic and dynamic load testing

Power

UPS systemsGeneratorsSwitchgear and power qualityProtection settings

Explained

Liquid coolingGPU load testingWater qualityLoop monitoringCommissioning

Equipment

Commissioning equipment

Manifold trolleyFlushing & refill cart

Tools

The full rangeSizing calculatorDatasheets

Services

Commissioning supportLoad bank hireHigh load simulationBespoke load banksSupply and installationMaintenance and repairDeployment and managementBuy or hireProjects

Company

AboutPartnersProjectsAcademyNewsEventsFAQ Speak to the team
Home/Explained/Commissioning and delivery/Where delays actually start
Commissioning and delivery

Where do commissioning delays actually start?

The delay is usually set months before anyone switches a load bank on.

Published 26 August 2026

0:44
Why the delay is set before testing begins
250Units, one controller
LiveFlow, temperature, pressure
UKHand built and tested
ExportableTest data for the record

Earlier than most people assume. Commissioning stalls when planning is left too late: kit booked at the last minute, an unclear site layout and nobody certain about the connections. Thinking through the full deployment from day one, including access routes, hose runs and power, removes most of that.

The full answer

The delay is not created during testing

Most people assume delays happen during testing, because that is when they become visible. In practice they start much earlier.

By the time a commissioning team is on site, most of the programme risk has already been set by decisions taken weeks or months before.

What a late-planned programme looks like

It has a consistent shape. The kit is booked at the last minute, the site layout is unclear and nobody is certain about the connections.

Engineers then spend site time fixing issues that should have been solved weeks earlier, which is the most expensive way to answer a question that was never difficult.

Planning the deployment from day one

The alternative is to think about the full deployment from the first conversation: timelines, access routes, hose runs, power requirements and how each unit will apply load in your specific space.

None of these are exotic questions. Answering them in advance costs a fraction of what answering them on site does.

Plan the test set-up early

PowerLoad supplies the load banks and supports the team that uses them. Planning the test set-up together early means infrastructure faults are found before they turn into commissioning problems.

That is where the real time saving on a programme comes from, and it happens long before anyone switches a load bank on.

More in this topic

Commissioning and delivery

FAQ

Answered

Long before the test window. They are typically set by late planning: equipment booked at the last minute, unclear site layout and unresolved questions about connections, all of which surface as lost time once engineers are on site.
Timelines, access routes, hose runs, power requirements and how each unit will apply load in the specific space, so the setup is understood before anything is delivered.
Where to next

Related reading

Programme not fully planned yet?

That is the right time to talk to us, not after the kit is booked.